# NEXTDC said 185 MW at M3 continued to be progressed at 31 December 2025.

> Cite as: PLOT record c/H5MT-JW v1, NEXTDC Limited (2025-12-31 to 2025-12-31), reported by source

- **Address:** c/H5MT-JW, version 1 of 1 (https://www.plot.eco/c/H5MT-JW)
- **Value:** 185 MW (IT capacity in progress)
- **About:** NEXTDC M3 · West Footscray
- **Kind:** Reported by source
- **Who said it:** Reported by the operator
- **Period:** 2025-12-31 to 2025-12-31
- **Checked:** Reviewed (step 3 of 4): PLOT checked the claim against its source. This is not independent verification. Checked by a person.
- **Open questions:** None open
- **Source:** 1H26 Record Results (ASX release, 25 February 2026) (NEXTDC Limited), p. 2, Development activity (p. 2) <https://announcements.asx.com.au/asxpdf/20260225/pdf/06wrhk4xg0qv34.pdf>
- **The snippet in PLOT:** <https://www.plot.eco/s/C3BW-F7?snippet=bb18e636-b369-4d9b-885d-543cdf9a578e>
- **How they know:** The company's half-year results release
- **Limitations:** Company-reported. 'Progressed' is the company's word; it doesn't say how far each part has got.
- **Editions:** october-26th-release
- **How we found this:** not recorded

## History
- Version 1 (this version): first published version

---
Machine-readable: https://www.plot.eco/c/H5MT-JW.json
Cite as: PLOT record c/H5MT-JW v1, NEXTDC Limited (2025-12-31 to 2025-12-31), reported by source