# NEXTDC Limited

> Cite as: PLOT record e/nextdc v1, compiled by PLOT (2024-07-01 to 2026-06-30), company summary

- **Address:** e/nextdc (https://www.plot.eco/e/nextdc)
- **Kind:** Company summary (compiled from the published claims listed)
- **Who said it:** Compiled by PLOT from the published claims listed
- **Period:** 2024-07-01 to 2026-06-30
- **Checked:** Reviewed (step 3 of 4): Its least-checked claim is reviewed. PLOT checked the claim against its source. This is not independent verification.
- **Open questions:** None open
- **Evidence shown:** Reviewed and from approved sources. 23 claims shown, all reviewed. 8 more are awaiting review and not shown.

An ASX-listed data centre operator, including M3 Melbourne in West Footscray.

## Claims (23)

### NEXTDC's FY26 annual report names Craig Scroggie as its CEO and managing director.

> Cite as: PLOT record c/Q44V-H6 v1, NEXTDC Limited (lodged with ASX, 27 August 2026) (undated), reported association

- **Address:** c/Q44V-H6, version 1 of 1 (https://www.plot.eco/c/Q44V-H6)
- **About:** Craig Scroggie → NEXTDC Limited
- **Kind:** Reported association
- **Who said it:** Reported by the operator
- **Period:** undated
- **Checked:** Reviewed (step 3 of 4): PLOT checked the claim against its source. This is not independent verification. Checked by a person.
- **Open questions:** None open
- **Source:** NEXTDC Limited FY26 Annual Report and Appendix 4E (year ended 30 June 2026) (NEXTDC Limited (lodged with ASX, 27 August 2026)), p. 13, p. 12 <https://announcements.asx.com.au/asxpdf/20260827/pdf/073c027z036kht.pdf>
- **The snippet in PLOT:** <https://www.plot.eco/s/K7KP-AB?snippet=0be442c3-9855-4c0e-9c7a-18e1543d0aa2>
- **Editions:** october-26th-release
- **How we found this:** not recorded

### NEXTDC's FY26 annual report names Michael Helmer as company secretary and chief risk officer, since February 2015.

> Cite as: PLOT record c/YN61-49 v1, NEXTDC Limited (lodged with ASX, 27 August 2026) (undated), reported association

- **Address:** c/YN61-49, version 1 of 1 (https://www.plot.eco/c/YN61-49)
- **About:** Michael Helmer → NEXTDC Limited
- **Kind:** Reported association
- **Who said it:** Reported by the operator
- **Period:** undated
- **Checked:** Reviewed (step 3 of 4): PLOT checked the claim against its source. This is not independent verification. Checked by a person.
- **Open questions:** None open
- **Source:** NEXTDC Limited FY26 Annual Report and Appendix 4E (year ended 30 June 2026) (NEXTDC Limited (lodged with ASX, 27 August 2026)), p. 31, p. 30, officers <https://announcements.asx.com.au/asxpdf/20260827/pdf/073c027z036kht.pdf>
- **The snippet in PLOT:** <https://www.plot.eco/s/K7KP-AB?snippet=2e8c7aea-9eee-46ee-a034-017cf2947c59>
- **Editions:** october-26th-release
- **How we found this:** not recorded

### In FY26 NEXTDC retired its standalone Climate and Nature Report and is reassessing how it aligns with the TNFD recommendations.

> Cite as: PLOT record c/50ZJ-V8 v1, NEXTDC Limited (2025-07-01 to 2026-06-30), reported by source

- **Address:** c/50ZJ-V8, version 1 of 1 (https://www.plot.eco/c/50ZJ-V8)
- **Value:** No standalone nature report; TNFD alignment under reassessment (Nature-related disclosure (framework used))
- **About:** NEXTDC Limited
- **Kind:** Reported by source
- **Who said it:** Reported by the operator
- **Period:** 2025-07-01 to 2026-06-30
- **Checked:** Reviewed (step 3 of 4): PLOT checked the claim against its source. This is not independent verification. Checked by a person.
- **Open questions:** None open
- **Source:** NEXTDC Limited FY26 Environmental, Social & Governance Report (NEXTDC Limited), p. 4, About this report (p. 4) <https://www.nextdc.com/hubfs/Financial%20Reports/FY26/FY26%20Environmental%2c%20Social%20%26%20Governance%20Report.pdf>
- **The snippet in PLOT:** <https://www.plot.eco/s/T7WJ-MS?snippet=aeddcd99-4e76-48e9-abd9-f4514293daa0>
- **How they know:** The company's FY26 ESG report
- **Limitations:** Company-reported. Climate disclosures moved into its mandatory AASB S2 report; nature reporting remains voluntary.
- **Editions:** nextdc-and-mobil-update
- **How we found this:** not recorded

### NEXTDC presents M3 Melbourne in West Footscray as one of its data centres.

> Cite as: PLOT record c/X12T-AK v1, NEXTDC (undated), reported association

- **Address:** c/X12T-AK, version 1 of 1 (https://www.plot.eco/c/X12T-AK)
- **About:** NEXTDC Limited → NEXTDC M3 · West Footscray
- **Kind:** Reported association
- **Who said it:** Reported by the operator
- **Period:** undated
- **Checked:** Reviewed (step 3 of 4): PLOT checked the claim against its source. This is not independent verification. Checked by a person.
- **Open questions:** None open
- **Source:** M3 Melbourne: facility specifications (NEXTDC), Page introduction <https://www.nextdc.com/data-centres/melbourne-data-centres/m3-melbourne>
- **The snippet in PLOT:** <https://www.plot.eco/s/VND3-CR?snippet=d7930ed4-fc70-4c3f-a2b9-2f70e38fccf3>
- **Editions:** nextdc-and-mobil-update
- **How we found this:** not recorded

### NEXTDC reports a portfolio power usage effectiveness (PUE) of 1.49 for FY26.

> Cite as: PLOT record c/6CS3-HT v1, NEXTDC Limited (2025-07-01 to 2026-06-30), reported by source

- **Address:** c/6CS3-HT, version 1 of 1 (https://www.plot.eco/c/6CS3-HT)
- **Value:** 1.49 PUE (Power usage effectiveness (PUE), portfolio)
- **About:** NEXTDC Limited
- **Kind:** Reported by source
- **Who said it:** Reported by the operator
- **Period:** 2025-07-01 to 2026-06-30
- **Checked:** Reviewed (step 3 of 4): PLOT checked the claim against its source. This is not independent verification. Checked by a person.
- **Open questions:** None open
- **Source:** NEXTDC Limited FY26 Environmental, Social & Governance Report (NEXTDC Limited), p. 7, Overview (p. 7) <https://www.nextdc.com/hubfs/Financial%20Reports/FY26/FY26%20Environmental%2c%20Social%20%26%20Governance%20Report.pdf>
- **The snippet in PLOT:** <https://www.plot.eco/s/T7WJ-MS?snippet=1825b50f-e729-4156-b1e0-3e1e546f4951>
- **How they know:** The company's energy data
- **Limitations:** A portfolio figure; M3's own PUE target (1.29) is a design target, not this. Not independently assured.
- **Editions:** nextdc-and-mobil-update
- **How we found this:** not recorded

### NEXTDC reports an average water usage effectiveness (WUE) of 2.40 across its portfolio in FY26.

> Cite as: PLOT record c/4KT8-WN v1, NEXTDC Limited (2025-07-01 to 2026-06-30), reported by source

- **Address:** c/4KT8-WN, version 1 of 1 (https://www.plot.eco/c/4KT8-WN)
- **Value:** 2.4 WUE (Water usage effectiveness (WUE), portfolio average)
- **About:** NEXTDC Limited
- **Kind:** Reported by source
- **Who said it:** Reported by the operator
- **Period:** 2025-07-01 to 2026-06-30
- **Checked:** Reviewed (step 3 of 4): PLOT checked the claim against its source. This is not independent verification. Checked by a person.
- **Open questions:** None open
- **Source:** NEXTDC Limited FY26 Environmental, Social & Governance Report (NEXTDC Limited), p. 27, Water stewardship: operational water management (p. 27) <https://www.nextdc.com/hubfs/Financial%20Reports/FY26/FY26%20Environmental%2c%20Social%20%26%20Governance%20Report.pdf>
- **The snippet in PLOT:** <https://www.plot.eco/s/T7WJ-MS?snippet=d66f0e7b-4c2f-4a6f-bdef-a941a155ea52>
- **How they know:** The company's water data
- **Limitations:** A portfolio average; the report doesn't state WUE's unit or how it is computed. Not independently assured.
- **Editions:** nextdc-and-mobil-update
- **How we found this:** not recorded

### NEXTDC reports consuming approximately 939.70 ML of water across its data centre portfolio in FY26.

> Cite as: PLOT record c/J1FN-DJ v1, NEXTDC Limited (2025-07-01 to 2026-06-30), reported by source

- **Address:** c/J1FN-DJ, version 1 of 1 (https://www.plot.eco/c/J1FN-DJ)
- **Value:** ≈ 939.7 ML (Water consumed)
- **About:** NEXTDC Limited
- **Kind:** Reported by source
- **Who said it:** Reported by the operator
- **Period:** 2025-07-01 to 2026-06-30
- **Checked:** Reviewed (step 3 of 4): PLOT checked the claim against its source. This is not independent verification. Checked by a person.
- **Open questions:** None open
- **Source:** NEXTDC Limited FY26 Environmental, Social & Governance Report (NEXTDC Limited), p. 27, Water stewardship: operational water management (p. 27) <https://www.nextdc.com/hubfs/Financial%20Reports/FY26/FY26%20Environmental%2c%20Social%20%26%20Governance%20Report.pdf>
- **The snippet in PLOT:** <https://www.plot.eco/s/T7WJ-MS?snippet=dec0f1f1-4d9d-4a7e-a417-98e781a58054>
- **How they know:** The company's water data (it says it is reconciling site and utility records)
- **Limitations:** Group total, not split by site; PLOT never divides it. Not independently assured. Site-level water balances are an FY27 priority, so M3's own use is still a gap (gap-m3-site-use).
- **Editions:** nextdc-and-mobil-update
- **How we found this:** not recorded

### NEXTDC reports total Scope 1 greenhouse gas emissions of 5,844 tCO2-e for FY26.

> Cite as: PLOT record c/AG63-J4 v1, NEXTDC Limited (lodged with ASX, 27 August 2026) (2025-07-01 to 2026-06-30), reported by source

- **Address:** c/AG63-J4, version 1 of 1 (https://www.plot.eco/c/AG63-J4)
- **Value:** 5844 tCO2-e (Scope 1 greenhouse gas emissions)
- **About:** NEXTDC Limited
- **Kind:** Reported by source
- **Who said it:** Reported by the operator
- **Period:** 2025-07-01 to 2026-06-30
- **Checked:** Reviewed (step 3 of 4): PLOT checked the claim against its source. This is not independent verification. Checked by a person.
- **Open questions:** None open
- **Source:** NEXTDC Limited FY26 Annual Report and Appendix 4E (year ended 30 June 2026) (NEXTDC Limited (lodged with ASX, 27 August 2026)), p. 83, Sustainability Report, Metrics and Targets (printed p. 82) <https://announcements.asx.com.au/asxpdf/20260827/pdf/073c027z036kht.pdf>
- **The snippet in PLOT:** <https://www.plot.eco/s/K7KP-AB?snippet=b7e32977-d91f-40d6-a913-fe7f98658309>
- **How they know:** GHG Protocol; first AASB S2 report; reviewed by the auditor to limited assurance
- **Limitations:** Group total, not split by site. May differ from NGER figures (different boundaries and methods), as the report says.
- **Editions:** nextdc-and-mobil-update
- **How we found this:** not recorded

### NEXTDC reports total Scope 2 greenhouse gas emissions (location-based) of 162,163 tCO2-e for FY26.

> Cite as: PLOT record c/MNYD-FW v1, NEXTDC Limited (lodged with ASX, 27 August 2026) (2025-07-01 to 2026-06-30), reported by source

- **Address:** c/MNYD-FW, version 1 of 1 (https://www.plot.eco/c/MNYD-FW)
- **Value:** 162163 tCO2-e (Scope 2 greenhouse gas emissions (location-based))
- **About:** NEXTDC Limited
- **Kind:** Reported by source
- **Who said it:** Reported by the operator
- **Period:** 2025-07-01 to 2026-06-30
- **Checked:** Reviewed (step 3 of 4): PLOT checked the claim against its source. This is not independent verification. Checked by a person.
- **Open questions:** None open
- **Source:** NEXTDC Limited FY26 Annual Report and Appendix 4E (year ended 30 June 2026) (NEXTDC Limited (lodged with ASX, 27 August 2026)), p. 83, Sustainability Report, Metrics and Targets (printed p. 82) <https://announcements.asx.com.au/asxpdf/20260827/pdf/073c027z036kht.pdf>
- **The snippet in PLOT:** <https://www.plot.eco/s/K7KP-AB?snippet=e5bfb374-017d-4b6c-8889-ec1d3d5bbe65>
- **How they know:** GHG Protocol Scope 2 Guidance; reviewed by the auditor to limited assurance
- **Limitations:** Group total, not split by site; M3's share is not stated and PLOT never divides it.
- **Editions:** nextdc-and-mobil-update
- **How we found this:** not recorded

### NEXTDC says it reports greenhouse gas emissions and energy information to the Clean Energy Regulator under the NGER Act.

> Cite as: PLOT record c/ACF4-GG v1, NEXTDC Limited (lodged with ASX, 27 August 2026) (2025-07-01 to 2026-06-30), reported by source

- **Address:** c/ACF4-GG, version 1 of 1 (https://www.plot.eco/c/ACF4-GG)
- **Value:** Reports under the NGER Act (as the company states) (Reports under the NGER Act)
- **About:** NEXTDC Limited
- **Kind:** Reported by source
- **Who said it:** Reported by the operator
- **Period:** 2025-07-01 to 2026-06-30
- **Checked:** Reviewed (step 3 of 4): PLOT checked the claim against its source. This is not independent verification. Checked by a person.
- **Open questions:** None open
- **Source:** NEXTDC Limited FY26 Annual Report and Appendix 4E (year ended 30 June 2026) (NEXTDC Limited (lodged with ASX, 27 August 2026)), p. 68, Sustainability Report, basis of preparation (printed p. 67) <https://announcements.asx.com.au/asxpdf/20260827/pdf/073c027z036kht.pdf>
- **The snippet in PLOT:** <https://www.plot.eco/s/K7KP-AB?snippet=352403a0-7766-4a87-97d7-b50d9f0d1936>
- **How they know:** Sustainability Report, basis of preparation
- **Limitations:** Company-reported; to confirm against the Clean Energy Regulator's published data.
- **Editions:** nextdc-and-mobil-update
- **How we found this:** not recorded

### NEXTDC's balance sheet shows current provisions of A$1,412 thousand at the end of FY26 (June 2026), for asset replacement and make good obligations.

> Cite as: PLOT record c/6W8N-9B v1, NEXTDC Limited (lodged with ASX, 27 August 2026) (? to 2026-06-30), reported by source

- **Address:** c/6W8N-9B, version 1 of 1 (https://www.plot.eco/c/6W8N-9B)
- **Value:** 1412 AUD thousand (Provisions, current (asset replacement and make good))
- **About:** NEXTDC Limited
- **Kind:** Reported by source
- **Who said it:** Reported by the operator
- **Period:** ? to 2026-06-30
- **Checked:** Reviewed (step 3 of 4): PLOT checked the claim against its source. This is not independent verification. Checked by a person.
- **Open questions:** None open
- **Source:** NEXTDC Limited FY26 Annual Report and Appendix 4E (year ended 30 June 2026) (NEXTDC Limited (lodged with ASX, 27 August 2026)), p. 94, Consolidated Balance Sheet, current liabilities: Provisions (printed p. 93) <https://announcements.asx.com.au/asxpdf/20260827/pdf/073c027z036kht.pdf>
- **The snippet in PLOT:** <https://www.plot.eco/s/K7KP-AB?snippet=895d440b-d228-4fe8-ae98-65361327bcd6>
- **How they know:** Consolidated Balance Sheet (audited); accounting policy note (k)
- **Limitations:** An accounting estimate of a future cost; not money spent. Not environmental remediation as such: make good obligations, mostly leases.
- **Editions:** nextdc-and-mobil-update
- **How we found this:** not recorded

### NEXTDC's balance sheet shows non-current provisions of A$3,321 thousand at the end of FY26 (June 2026), for asset replacement and make good obligations.

> Cite as: PLOT record c/AS4P-ZG v1, NEXTDC Limited (lodged with ASX, 27 August 2026) (? to 2026-06-30), reported by source

- **Address:** c/AS4P-ZG, version 1 of 1 (https://www.plot.eco/c/AS4P-ZG)
- **Value:** 3321 AUD thousand (Provisions, non-current (asset replacement and make good))
- **About:** NEXTDC Limited
- **Kind:** Reported by source
- **Who said it:** Reported by the operator
- **Period:** ? to 2026-06-30
- **Checked:** Reviewed (step 3 of 4): PLOT checked the claim against its source. This is not independent verification. Checked by a person.
- **Open questions:** None open
- **Source:** NEXTDC Limited FY26 Annual Report and Appendix 4E (year ended 30 June 2026) (NEXTDC Limited (lodged with ASX, 27 August 2026)), p. 94, Consolidated Balance Sheet, non-current liabilities: Provisions (printed p. 93) <https://announcements.asx.com.au/asxpdf/20260827/pdf/073c027z036kht.pdf>
- **The snippet in PLOT:** <https://www.plot.eco/s/K7KP-AB?snippet=895d440b-d228-4fe8-ae98-65361327bcd6>
- **How they know:** Consolidated Balance Sheet (audited); accounting policy note (k)
- **Limitations:** An accounting estimate of a future cost; not money spent.
- **Editions:** nextdc-and-mobil-update
- **How we found this:** not recorded

### NEXTDC's Board approved a target of net zero Scope 1 and Scope 2 greenhouse gas emissions by 2050.

> Cite as: PLOT record c/H9SX-7D v1, NEXTDC Limited (lodged with ASX, 27 August 2026) (? to 2050-12-31), target (not achieved performance)

- **Address:** c/H9SX-7D, version 1 of 1 (https://www.plot.eco/c/H9SX-7D)
- **Value:** Net zero Scope 1 and Scope 2 by 2050 (Emissions target)
- **About:** NEXTDC Limited
- **Kind:** Target (not achieved performance)
- **Who said it:** Reported by the operator
- **Period:** ? to 2050-12-31
- **Checked:** Reviewed (step 3 of 4): PLOT checked the claim against its source. This is not independent verification. Checked by a person.
- **Open questions:** None open
- **Source:** NEXTDC Limited FY26 Annual Report and Appendix 4E (year ended 30 June 2026) (NEXTDC Limited (lodged with ASX, 27 August 2026)), p. 83, Sustainability Report, Net Zero target (printed p. 82) <https://announcements.asx.com.au/asxpdf/20260827/pdf/073c027z036kht.pdf>
- **The snippet in PLOT:** <https://www.plot.eco/s/K7KP-AB?snippet=a60041ea-4583-40d8-a1c1-12697e775cfd>
- **How they know:** Sustainability Report
- **Limitations:** A promise; to be placed beside what records show over time (C11). No score.
- **Editions:** nextdc-and-mobil-update
- **How we found this:** not recorded

### NEXTDC's consolidated total assets at the end of FY26 (June 2026) were A$10,236,587 thousand.

> Cite as: PLOT record c/TPYH-5M v1, NEXTDC Limited (lodged with ASX, 27 August 2026) (? to 2026-06-30), reported by source

- **Address:** c/TPYH-5M, version 1 of 1 (https://www.plot.eco/c/TPYH-5M)
- **Value:** 10236587 AUD thousand (Total assets (consolidated))
- **About:** NEXTDC Limited
- **Kind:** Reported by source
- **Who said it:** Reported by the operator
- **Period:** ? to 2026-06-30
- **Checked:** Reviewed (step 3 of 4): PLOT checked the claim against its source. This is not independent verification. Checked by a person.
- **Open questions:** None open
- **Source:** NEXTDC Limited FY26 Annual Report and Appendix 4E (year ended 30 June 2026) (NEXTDC Limited (lodged with ASX, 27 August 2026)), p. 94, Consolidated Balance Sheet, total assets (printed p. 93) <https://announcements.asx.com.au/asxpdf/20260827/pdf/073c027z036kht.pdf>
- **The snippet in PLOT:** <https://www.plot.eco/s/K7KP-AB?snippet=acbb1ef4-60e2-4e55-85bb-2edd37314b93>
- **How they know:** Consolidated Balance Sheet (audited)
- **Limitations:** Used for PLOT's estimate of its reporting group (C03).
- **Editions:** nextdc-and-mobil-update
- **How we found this:** not recorded

### NEXTDC's FY25 Climate and Nature Report applied the TNFD's LEAP approach and screened its operational sites for nearby protected areas, biodiversity and water risk.

> Cite as: PLOT record c/9A0K-T1 v1, NEXTDC Limited (2024-07-01 to 2025-06-30), reported by source

- **Address:** c/9A0K-T1, version 1 of 1 (https://www.plot.eco/c/9A0K-T1)
- **Value:** Voluntary TNFD-aligned LEAP assessment, with desktop screening of all 18 operational sites (Nature-related disclosure (framework used))
- **About:** NEXTDC Limited
- **Kind:** Reported by source
- **Who said it:** Reported by the operator
- **Period:** 2024-07-01 to 2025-06-30
- **Checked:** Reviewed (step 3 of 4): PLOT checked the claim against its source. This is not independent verification. Checked by a person.
- **Open questions:** None open
- **Source:** NEXTDC Limited FY25 Climate and Nature Report (NEXTDC Limited), p. 2, Introduction (p. 2) <https://www.nextdc.com/hubfs/ASX%20Announcements/FY25%20Climate%20and%20Nature%20Report.pdf>
- **The snippet in PLOT:** <https://www.plot.eco/s/YNJQ-NC?snippet=fa4dac04-b2fe-449d-a2c0-ceec3fc18b39>
- **How they know:** The company's voluntary climate and nature report
- **Limitations:** Voluntary and company-reported; a desktop screening, not a site survey.
- **Editions:** nextdc-and-mobil-update
- **How we found this:** not recorded

### NEXTDC's FY25 screening counts 10 critically endangered species (IUCN Red List) around its M3 data centre, within the radius its table states.

> Cite as: PLOT record c/0FRS-8Z v1, NEXTDC Limited (2024-07-01 to 2025-06-30), context

- **Address:** c/0FRS-8Z, version 1 of 1 (https://www.plot.eco/c/0FRS-8Z)
- **Value:** 10 species (Critically endangered species (IUCN) recorded within 50 km)
- **About:** NEXTDC Limited
- **Kind:** Context
- **Who said it:** Reported by the operator
- **Period:** 2024-07-01 to 2025-06-30
- **Checked:** Reviewed (step 3 of 4): PLOT checked the claim against its source. This is not independent verification. Checked by a person.
- **Open questions:** None open
- **Source:** NEXTDC Limited FY25 Climate and Nature Report (NEXTDC Limited), p. 12, Table 2, Site based biodiversity and water risk screening, row M3 (p. 12) <https://www.nextdc.com/hubfs/ASX%20Announcements/FY25%20Climate%20and%20Nature%20Report.pdf>
- **The snippet in PLOT:** <https://www.plot.eco/s/YNJQ-NC?snippet=37eada80-3d18-40b7-98a7-e5d937179e58>
- **How they know:** NEXTDC's desktop screening of each site within 50 km: IBAT (protected areas, Key Biodiversity Areas), Global Ramsar mapping and the IUCN Red List
- **Limitations:** A count of what lies within 50 km of the site, from global databases: it describes the Melbourne region (M1 and M2 have almost the same counts), not the site, so PLOT shows it only in the company's nature reporting (C05), not on M3's page; and says nothing about any effect of the data centre. Company-reported screening.
- **Editions:** nextdc-and-mobil-update
- **How we found this:** not recorded

### NEXTDC's FY25 screening counts 147 protected areas around its M3 data centre, within the radius its table states.

> Cite as: PLOT record c/XF36-N9 v1, NEXTDC Limited (2024-07-01 to 2025-06-30), context

- **Address:** c/XF36-N9, version 1 of 1 (https://www.plot.eco/c/XF36-N9)
- **Value:** 147 count (Protected areas within 50 km)
- **About:** NEXTDC Limited
- **Kind:** Context
- **Who said it:** Reported by the operator
- **Period:** 2024-07-01 to 2025-06-30
- **Checked:** Reviewed (step 3 of 4): PLOT checked the claim against its source. This is not independent verification. Checked by a person.
- **Open questions:** None open
- **Source:** NEXTDC Limited FY25 Climate and Nature Report (NEXTDC Limited), p. 12, Table 2, Site based biodiversity and water risk screening, row M3 (p. 12) <https://www.nextdc.com/hubfs/ASX%20Announcements/FY25%20Climate%20and%20Nature%20Report.pdf>
- **The snippet in PLOT:** <https://www.plot.eco/s/YNJQ-NC?snippet=37eada80-3d18-40b7-98a7-e5d937179e58>
- **How they know:** NEXTDC's desktop screening of each site within 50 km: IBAT (protected areas, Key Biodiversity Areas), Global Ramsar mapping and the IUCN Red List
- **Limitations:** A count of what lies within 50 km of the site, from global databases: it describes the Melbourne region (M1 and M2 have almost the same counts), not the site, so PLOT shows it only in the company's nature reporting (C05), not on M3's page; and says nothing about any effect of the data centre. Company-reported screening.
- **Editions:** nextdc-and-mobil-update
- **How we found this:** not recorded

### NEXTDC's FY25 screening counts 2 Ramsar wetlands around its M3 data centre, within the radius its table states.

> Cite as: PLOT record c/W1S3-6J v1, NEXTDC Limited (2024-07-01 to 2025-06-30), context

- **Address:** c/W1S3-6J, version 1 of 1 (https://www.plot.eco/c/W1S3-6J)
- **Value:** 2 count (Ramsar wetlands within 50 km)
- **About:** NEXTDC Limited
- **Kind:** Context
- **Who said it:** Reported by the operator
- **Period:** 2024-07-01 to 2025-06-30
- **Checked:** Reviewed (step 3 of 4): PLOT checked the claim against its source. This is not independent verification. Checked by a person.
- **Open questions:** None open
- **Source:** NEXTDC Limited FY25 Climate and Nature Report (NEXTDC Limited), p. 12, Table 2, Site based biodiversity and water risk screening, row M3 (p. 12) <https://www.nextdc.com/hubfs/ASX%20Announcements/FY25%20Climate%20and%20Nature%20Report.pdf>
- **The snippet in PLOT:** <https://www.plot.eco/s/YNJQ-NC?snippet=37eada80-3d18-40b7-98a7-e5d937179e58>
- **How they know:** NEXTDC's desktop screening of each site within 50 km: IBAT (protected areas, Key Biodiversity Areas), Global Ramsar mapping and the IUCN Red List
- **Limitations:** A count of what lies within 50 km of the site, from global databases: it describes the Melbourne region (M1 and M2 have almost the same counts), not the site, so PLOT shows it only in the company's nature reporting (C05), not on M3's page; and says nothing about any effect of the data centre. Company-reported screening.
- **Editions:** nextdc-and-mobil-update
- **How we found this:** not recorded

### NEXTDC's FY25 screening counts 4 Key Biodiversity Areas around its M3 data centre, within the radius its table states.

> Cite as: PLOT record c/WZ04-DB v1, NEXTDC Limited (2024-07-01 to 2025-06-30), context

- **Address:** c/WZ04-DB, version 1 of 1 (https://www.plot.eco/c/WZ04-DB)
- **Value:** 4 count (Key Biodiversity Areas within 50 km)
- **About:** NEXTDC Limited
- **Kind:** Context
- **Who said it:** Reported by the operator
- **Period:** 2024-07-01 to 2025-06-30
- **Checked:** Reviewed (step 3 of 4): PLOT checked the claim against its source. This is not independent verification. Checked by a person.
- **Open questions:** None open
- **Source:** NEXTDC Limited FY25 Climate and Nature Report (NEXTDC Limited), p. 12, Table 2, Site based biodiversity and water risk screening, row M3 (p. 12) <https://www.nextdc.com/hubfs/ASX%20Announcements/FY25%20Climate%20and%20Nature%20Report.pdf>
- **The snippet in PLOT:** <https://www.plot.eco/s/YNJQ-NC?snippet=37eada80-3d18-40b7-98a7-e5d937179e58>
- **How they know:** NEXTDC's desktop screening of each site within 50 km: IBAT (protected areas, Key Biodiversity Areas), Global Ramsar mapping and the IUCN Red List
- **Limitations:** A count of what lies within 50 km of the site, from global databases: it describes the Melbourne region (M1 and M2 have almost the same counts), not the site, so PLOT shows it only in the company's nature reporting (C05), not on M3's page; and says nothing about any effect of the data centre. Company-reported screening.
- **Editions:** nextdc-and-mobil-update
- **How we found this:** not recorded

### NEXTDC's FY26 annual report contains its first sustainability report under AASB S2.

> Cite as: PLOT record c/WPQM-D5 v1, NEXTDC Limited (lodged with ASX, 27 August 2026) (2025-07-01 to 2026-06-30), reported by source

- **Address:** c/WPQM-D5, version 1 of 1 (https://www.plot.eco/c/WPQM-D5)
- **Value:** First AASB S2 report: FY26 (Mandatory climate-related disclosures (AASB S2))
- **About:** NEXTDC Limited
- **Kind:** Reported by source
- **Who said it:** Reported by the operator
- **Period:** 2025-07-01 to 2026-06-30
- **Checked:** Reviewed (step 3 of 4): PLOT checked the claim against its source. This is not independent verification. Checked by a person.
- **Open questions:** None open
- **Source:** NEXTDC Limited FY26 Annual Report and Appendix 4E (year ended 30 June 2026) (NEXTDC Limited (lodged with ASX, 27 August 2026)), p. 16, Sustainability highlights (printed p. 15) <https://announcements.asx.com.au/asxpdf/20260827/pdf/073c027z036kht.pdf>
- **The snippet in PLOT:** <https://www.plot.eco/s/K7KP-AB?snippet=6fa8a93d-f168-46ed-bffb-962b1f58acf3>
- **How they know:** Annual report
- **Limitations:** The company's own statement of what it reported; it prevails over PLOT's estimate of its reporting group.
- **Editions:** nextdc-and-mobil-update
- **How we found this:** not recorded

### NEXTDC's FY26 double materiality assessment identified biodiversity as a peripheral topic for the company.

> Cite as: PLOT record c/8BTX-BD v1, NEXTDC Limited (2025-07-01 to 2026-06-30), reported by source

- **Address:** c/8BTX-BD, version 1 of 1 (https://www.plot.eco/c/8BTX-BD)
- **Value:** Peripheral topic (double materiality assessment, FY26) (Biodiversity in the company's materiality assessment)
- **About:** NEXTDC Limited
- **Kind:** Reported by source
- **Who said it:** Reported by the operator
- **Period:** 2025-07-01 to 2026-06-30
- **Checked:** Reviewed (step 3 of 4): PLOT checked the claim against its source. This is not independent verification. Checked by a person.
- **Open questions:** None open
- **Source:** NEXTDC Limited FY26 Environmental, Social & Governance Report (NEXTDC Limited), p. 4, About this report (p. 4) <https://www.nextdc.com/hubfs/Financial%20Reports/FY26/FY26%20Environmental%2c%20Social%20%26%20Governance%20Report.pdf>
- **The snippet in PLOT:** <https://www.plot.eco/s/T7WJ-MS?snippet=0fb9550a-4148-4413-8b96-c39f37b590a8>
- **How they know:** The company's own double materiality assessment
- **Limitations:** The company's own judgement; it says it will revisit nature-related materiality as its business and the frameworks evolve.
- **Editions:** nextdc-and-mobil-update
- **How we found this:** not recorded

### NEXTDC's revenue from ordinary activities for the year to June 2026 (FY26) was A$496,492 thousand.

> Cite as: PLOT record c/FCYR-B1 v1, NEXTDC Limited (lodged with ASX, 27 August 2026) (2025-07-01 to 2026-06-30), reported by source

- **Address:** c/FCYR-B1, version 1 of 1 (https://www.plot.eco/c/FCYR-B1)
- **Value:** 496492 AUD thousand (Revenue from ordinary activities (consolidated))
- **About:** NEXTDC Limited
- **Kind:** Reported by source
- **Who said it:** Reported by the operator
- **Period:** 2025-07-01 to 2026-06-30
- **Checked:** Reviewed (step 3 of 4): PLOT checked the claim against its source. This is not independent verification. Checked by a person.
- **Open questions:** None open
- **Source:** NEXTDC Limited FY26 Annual Report and Appendix 4E (year ended 30 June 2026) (NEXTDC Limited (lodged with ASX, 27 August 2026)), p. 1, Appendix 4E, results for announcement to the market (p. 1) <https://announcements.asx.com.au/asxpdf/20260827/pdf/073c027z036kht.pdf>
- **The snippet in PLOT:** <https://www.plot.eco/s/K7KP-AB?snippet=d2f420c9-322c-4a57-8bbd-8bc2149ecc80>
- **How they know:** Appendix 4E; the consolidated statement of comprehensive income is audited
- **Limitations:** Used for PLOT's estimate of its reporting group (C03).
- **Editions:** nextdc-and-mobil-update
- **How we found this:** not recorded

### The ABN register records NEXTDC Limited as an Australian public company with an active ABN since 2010.

> Cite as: PLOT record c/5K3G-C8 v1, Australian Business Register (Current details, extracted 22 Oct 2026), legal or financial record

- **Address:** c/5K3G-C8, version 1 of 1 (https://www.plot.eco/c/5K3G-C8)
- **Value:** Australian Public Company; ABN active (Company type (ABN register))
- **About:** NEXTDC Limited
- **Kind:** Legal or financial record
- **Who said it:** Legal register
- **Period:** Current details, extracted 22 Oct 2026
- **Checked:** Reviewed (step 3 of 4): PLOT checked the claim against its source. This is not independent verification. Checked by a person.
- **Open questions:** None open
- **Source:** ABN Lookup: NEXTDC LIMITED (ABN 35 143 582 521) (Australian Business Register), ABN Lookup, current details <https://abr.business.gov.au/ABN/View?id=35143582521>
- **The snippet in PLOT:** <https://www.plot.eco/s/S77S-SK?snippet=4749887c-20fd-481e-9650-3d4f5f891253>
- **How they know:** ABN Lookup current details
- **Editions:** nextdc-and-mobil-update
- **How we found this:** not recorded

## Next steps (0)
- None published.

---
Machine-readable: https://www.plot.eco/e/nextdc.json
Cite as: PLOT record e/nextdc v1, compiled by PLOT (2024-07-01 to 2026-06-30), company summary