# It's all systems go Victoria: NEXTDC unveils plans for 150MW hyperscale campus in Melbourne's west

- Address: s/B29Z-J1 (https://www.plot.eco/s/B29Z-J1)
- Kind: Source: webpage, company author. A source is where claims come from; it is not itself a claim.
- Publisher: NEXTDC Ltd
- Date or edition: not recorded
- Licence: not recorded (All rights reserved by NEXTDC Ltd. PLOT keeps a private copy and shows only short quoted passages with a link to the page.)
- How PLOT found it: Found before sourcing protocol v0.1 (pre-protocol)
- Stored copy: retrieved 2026-10-21, sha256 e9a439139d9bafa321d7ccb33efe2473b5d244293d43d99d7482fe7bc255ff8e, 1 pages
- Original: https://www.nextdc.com/news/its-all-systems-go-victoria-nextdc-unveils-plans-150mw-hyperscale-campus-melbournes-west

## Snippets cited by published claims (3; 3 claims)

### News release

> West Footscray is an emerging digital hub, and we are excited for the future

- c/YK9M-CC: In August 2021 NEXTDC's chief executive, Craig Scroggie, called West Footscray an emerging digital hub when NEXTDC announced its upgraded M3 plans. (https://www.plot.eco/c/YK9M-CC)

### News release, 12 Aug 2021

> The full M3 site spans a massive 100,000sqm and will target 150MW of critical capacity at full fitout.

- c/511Z-VC: In August 2021 NEXTDC said the full M3 site, 100,000 square metres, would target 150 MW of critical capacity at full fit-out. (https://www.plot.eco/c/511Z-VC)

### News release, 12 Aug 2021

> NEXTDC has received formal planning consent to proceed with the construction of our new hyperscale technology campus

- c/9KEW-EB: NEXTDC said in August 2021 that it had received formal planning consent to build M3. (https://www.plot.eco/c/9KEW-EB)

Cite as: NEXTDC Ltd, It's all systems go Victoria: NEXTDC unveils plans for 150MW hyperscale campus in Melbourne's west. PLOT source s/B29Z-J1