PLOT c/PZP1-PA · version 1 of 1
NEXTDC says M3's later construction stages are tracking at approximately 27% lower embodied carbon than the Stage 1 baseline.
≈ 27 %Embodied carbon below the project's baseline
About NEXTDC M3 · West Footscray
- Kind
- Modelled or forecast
- Who said it
- Reported by the operator
- Period
- ? to 2026-06-30
- Checked
- Reviewed (step 3 of 4): PLOT checked the claim against its source. This is not independent verification.
- Open questions
- None openOpen questions and challenges are counted publicly; their text is published when they are resolved.
- Where it says so
- NEXTDC Limited FY26 Environmental, Social & Governance Report (on nextdc.com) (NEXTDC Limited) · View in PLOT — p. 3, Chair and CEO message (p. 3)
- How they know
- The company's embodied-carbon tracking for the project (method not published)
- Limitations
- An estimate while building, against the company's own baseline; the baseline and method aren't published. Company-reported.
- Framework targets
- none linked
- Editions
- nextdc-and-mobil-update
How we found this
Not recorded for this claim.
Cite as: PLOT record c/PZP1-PA v1, NEXTDC Limited (? to 2026-06-30), modelled or forecast
History (1)
- Version 1 (shown here): first published version